Capital Improvement Projects

The Capital Improvement Division provides administration of the city's 5 year capital improvement program (CIP). This division oversees the turnkey contract management operation of circulation, infrastructure, Community Services & Redevelopment Agency projects, from project initiation to contract closeout.

Staff is responsible for preparing Requests for Proposals to secure professional services for design and construction of public works and park projects. Staff also arranges for needed right-of-way acquisitions for CIP project construction, completes studies and designs in a timely manner, calculates accurate estimates, and manages the construction and thorough inspection of those projects.

This division of the Public Works Department also reviews and approves all consultant plans; conducts the public bidding process; coordinates with other City Departments, utility companies and government agencies; and performs construction inspection. The Master Planning and Conceptual Design of all City parks is directed through the Temecula Community Services District and transferred to the Capital Projects Program for preparation of the plans and specifications, and subsequent construction.

CAPITAL IMPROVEMENT PROJECTS
Monthly Activity Report
July / August 2008 

Prepared By: Amer Attar
Submitted by: William G. Hughes  
Date: August 26, 2008

 
PROJECTS UNDER CONSTRUCTION 

1.  Fire Station - Northeast Site (Roripaugh Ranch)

This project will construct a new fire station in the north part of the City.  The majority of work was completed by April of 2006.  Roripaugh Developer (Ashby) schedule shows access and utilities to the site in August 2007.  Because of this there was cost to re-mobilize and complete the project when the aforementioned items are complete, these costs are reflected in an approved change order total, which is the responsibility of the developer.  In addition, a fire engine/truck venting system (requested/added on 2/06) will be installed when the Contractor is re-mobilized; this cost is also included in the approved change order total.

2.  Temecula Education Center- Rough Grading

This project will provide for the grading of the old Temecula Education Center site. All work was completed on March 28, 2007.  NPDES work on the site was completed in March of 2008.  Additional work is planned to restore the RCWD site permanently and to make the site easier to maintain NPDES compliance is estimated to start in July of 2008.  NPDES maintenance will be an ongoing expense.

3.  Murrieta Creek Multi Purpose Trail

This project will build equestrian and bike trails along Murrieta Creek between Rancho California Road and Diaz Road.  On the north side of the project, the contractor has completed the grading, the installation of the mainline irrigation, the mow curb, the DG and the AC. They are working on the irrigation laterals.  On the south side, the contractor has completed the grading and is almost done installing the irrigation mainline. Soil quality issues are being looked into.

4.  Traffic Signal Installation – Rancho California Road at Business Park West

Under this project, a traffic signal will be installed on Rancho California Road at Business Park Drive West. All work on this project is complete. The signal was turned on on Tuesday 02/26/08. We are working with the contractor to close out this contract.

5.  Old Town Infrastructure Projects - Street Improvements, Mercedes St (2nd - 6th) & the Realignment of Main St. and Construction of the Town Square

This project includes the construction of the Town Square and street improvements on Mercedes & Main Streets. On March 18, 2008, the City Council awarded the construction contract L H Engineering Company, Inc for $3,458,495.00. Work is ongoing on storm drains, sewer, water systems and the Town Square.

6.  Old Town Infrastructure Projects - Underground Utility District

This project will effectively underground all overhead utility lines along Old Town Front Street, between 2nd and 6th streets, all of Main Street east of Murrieta Creek and Mercedes Street between 2nd and 6th streets.  Herman Weissker was awarded the work at the 3/18/08, City Council Meeting.  Work is currently underway along Main Street.

7.  Citywide Concrete Repairs  FY 2007-08

This project will remove and replace various concrete improvements including sidewalk, curb and gutter, cross gutters, driveways approaches, and under sidewalk drains.  Contract work was completed on June 24, 2008.  City Council accepted the project as complete at the July 22, 2008, City Council meeting.

8.  Citywide Slurry Seal Project FY 2007-2008

This project will slurry seal streets mainly in the Paloma del Sol area. Contract was awarded to All American Asphalt for $361,199.88 on 04/08/06 and the pre-construction meeting was held on 05/29/2008.  Construction began on 06/30/08.

9.  Roller Hockey Rink Dasher Board System

This project will replace the boards at the existing Roller Hockey Rink. The dasher board system has been installed and the rink was resurfaced. The contractor (YAKAR) has ordered approximately 120 additional anchor bolts for the dasher board system that Building and Safety has determined are necessary to meet the wind load requirements of the Building Code. These will be installed the week of 8/18/08

10.  Pechanga Parkway  Improvements – Phase II (Temecula Parkway (formerly SR 79 South to Pechanga Road)

 This project will widen Pechanga Parkway (formerly Pala Road) to its ultimate width from the Pechanga Parkway Bridge to Pechanga road.  Construction began on July 7, 2008 Construction items that will occur during the month of August is as follows: grading, curb and gutter, catch basins, storm drain, pavement, aggregate base, and traffic signals. The traffic signal at Muirfield Drive will be removed during the week of August 18. The new traffic signal at Muirfield Drive is scheduled to be installed during the month of November. The final section of the Pechanga Tribe's Recycled Waterline project between Loma Linda Road and Rainbow Canyon Road started on July 14 and will be complete by November 1.

11.  Old Town Infrastructure Projects - Site Demolition and Site Preparation

This project involves demolishing the existing non-historic structures on the City owned parcels at the intersection Main and Mercedes to make way for the Main Street Realignment and the Old Town Parking Structure. This project is complete. The City Council accepted the project as complete at the July 22, 2008, City Council meeting.

 

PROJECTS BEING ADVERTISED FOR BIDS

 1.  Old Town Infrastructure Projects - Parking Structure & Office/Retail frontage

This project will construct a parking structure, including office and retail frontage as part of phase 1 of Old Town Civic Center project.  The project is being advertised for construction bids. RFI are coming in. Bids open on 8/19/8. Addendum 1 went out 8/6/08. Two Encroachment Permit applications (for retaining wall & SD) are under review with Caltrans. The Underground Fire Protection plan is pending RCWD approval. The project is anticipated to be awarded on August 26, 2008.

2.  Old Town Civic Center Phase 2

Under this project the design and construction documents for phase two of the Civic Center Project will be developed. The project is being advertised for construction bids. Bids open on 9/3/08. 19 General contractors were pre-qualified. Award of contract is anticipated on 9/9/8.

 

 PROJECTS IN DESIGN

1.      Pechanga Parkway Storm Drain Improvements – Environmental Mitigation

This project includes construction of new wetlands as part of the Wolf Valley Creek Channel - Stage I. The mitigation site is located along the north bank of Temecula Creek (within the floodplain and floodway area). The environmental regulatory agencies have approved this new mitigation area. RCFCD had no significant comments re the installation work. Mylars are currently ready for signature. The contract bid document was prepared, reviewed, and is being revised to incorporate the final corrections. The appraisal for three easements is now complete; offers for purchase of the property were made.

 2.      Murrieta Creek Bridge - Overland Drive Extension to Diaz Road

This project includes studying alignments, design and construction of an extension of Overland Drive, westerly to Diaz Road, including a new bridge over Murrieta Creek.  Coordination with RCFC & WCD and the U. S. Army Corp of Engineers is required he extra work authorization to complete the 100% design submittal has been signed.  The consultant has started the final design and a design meeting will be scheduled to go over the final requirements of the project.          

3.      Main Street Bridge Over Murrieta Creek (Replacement)

This project will replace the existing Main Street Bridge over Murrieta Creek. Design consultant Simon Wong Engineering (SWE) and the City are continuing to pursue environmental permitting and coordination issues associated with pursuing the bridge replacement as a project separate from the Army Corps of Engineer's Murrieta Creek improvement project.  Environmental consultant EDAW has completed biological field studies, and has submitted for staff review the Natural Environment Study Report, the Historic Property Survey Report, and the Jurisdictional Delineation Report for Waters of the U.S.  SWE submitted 90% PS&E on 7/14/08, which are also currently under staff review.  100% PS&E anticipated in September, 2008.

 4.    Pedestrian/Bicycle Bridge Over Santa Gertrudis Creek

This project includes the construction of an approx. 150' ped/bike bridge over Santa Gertrudis Creek near Chaparral H.S. This is a federally funded project, which will involve a NEPA document. Preliminary Environmental Study (PES) form is to be submitted to Caltrans within the next month.  Coordination between the City and Rancho California Water District to acquire a portion of an RCWD-owned parcel needed to construct the bridge continues. Staff review comments on 30% plans were returned to the design consultant on 6/19/08; 60% submittal is anticipated by the end of August.

5.    Ronald Reagan Sports Park Channel Silt Removal & Desiltation Pond

This project includes restoring the Best Management Practices (BMP) of the Stormwater Pollution Prevention Plan (SWPPP), the Water Quality Management Plan (WQMP) and the requirement of RWQCB by desilting the basin located near the Sports Park. Staff is reviewing 90% design submittal. 401 Certification has been received and the Streambed Alteration Agreement is expected shortly. Final negotiation with USF&WS and CDFG for mitigation requirements is pending.

 6.    Western Bypass Bridge Over Murrieta Creek

This project involves the design and construction of a new bridge over Murrieta Creek at the westerly terminus of SR-79S and an extension of Pujol Street to the new structure. Once constructed, this will serve as the southerly connection of the Western Bypass Corridor Staff has received an amended proposal for the design. The proposal received City Council Approval on June 24, 2008 and work is restarted.

7.    Temecula Community Center Expansion

This project will add approximately 4000 square feet of space to the existing Temecula Community Center to accommodate more human services programs. Comments have been received from the EDA and the project has been cleared to go to bid. The plans and specifications are prepared for bid advertisement. The project will be bid for thirty days. The project cost estimate is $1,500,00. The plans for the Escallier House and barn are being revised to re route the accessible path of travel to the front of the buildings.

8.    Redhawk Park Improvements, Four Sites

This project will add amenities to four park sites in the recently annexed Redhawk area. Due to budgetary restraints, the construction was divided into phases over a number of years. At the December 11, 2007 meeting, the City Council approved an agreement with RJM for the construction drawings of the chosen amenities, which include a half court basketball court, ADA accessible parking, and dog park at Redhawk Community Park; a seatwall and shade structure at Sunset Park. A kick off meeting with the design consultant was held on 02/05/08. The preparation of the construction drawings continues.

9.    Temecula Parkway (formerly 79 South) Park & Ride

This project will design and construct a park and ride facility on Temecula Parkway (formerly 79 South) at La Paz.  The project is still on hold pending TCSD and Planning review. The new City Ordinance has been forwarded to the design consultant for his review. It is anticipated that the landscape design will change to adopt these new measures.

10.    De Portola Road Pavement Rehabilitation Project (from Jedediah Smith to Margarita)

This project includes rehabilitating De Portola Road from Jedediah Smith Road to Margarita Road. This is a federally funded project. The Environmental Document (Categorical Exclusion) was approved by Caltrans on August 8, 2007. Design consultant submitted 90% plans on 5/28/08; 100% PS&E submittal is expected by the end of August.  Request for Federal construction authorization was submitted on 6/24/2008; approval is anticipated by mid-September.

 11.   79 South to Pechanga Parkway - Dual Right Turn Lanes

This project includes the design and construction of two right turn lanes on eastbound Temecula Parkway (formerly State Route 79 South) to southbound Pechanga Parkway. The design includes the widening of Temecula Parkway and relocation of traffic signal poles.  100% design plans are complete. The City is in the process of purchasing the required right of way. Once the needed right of way is acquired, construction will be scheduled.

12.   Santiago Detention Basin

This project includes the design and construction of a detention basin. The proposed basin (1 acre in size) is located on the south side of Santiago Rd between Vallejo Ave and Orsmby Rd. 100% design plans have been reviewed and minor comments will be provided to the consultant for incorporation into the plans.

13.    Pavement Rehabilitation – STPL Project

This project will rehab Rancho California Road from Ynez Rd. to the City limits on the east. Consultant is working on the 100% design package.  The City received the signed PES form and the Categorical Exclusion (CE) from Caltrans. The request for Federal construction authorization was submitted on June 24, 2008. The project will go to construction in late 2008.

14.     Winchester Road/79-North Corridor Beautification

This federally funded project will design and construct landscaping and irrigation enhancements to the existing raised medians along Winchester Road between Ynez Road and the easterly City limit.  The consultant is working on the 100% design package. The City received the signed PES form and the Categorical Exclusion (CE) from Caltrans. The City has received approval from RCWD for the installation of the recycled waterline.

 15.     French Valley Parkway Phase 1 - Southbound Off-Ramp to Jefferson, Auxiliary Lane, and Widening the Bridge over Santa Gertrudis Creek at the Winchester Southbound Off-ramp

A southbound off-Ramp to Jefferson, an auxiliary lane, and widening the bridge over Santa Gertrudis Creek at the Winchester southbound off-ramp are the components of Phase 1. The City and Caltrans have agreed that immediate action is required to relieve congestion at the Winchester Road southbound off-ramp. Status is as follows:

Ø      PS&E – Consultant is preparing 95% plans (retaining walls and landscape/irrigation).

Ø      Type Selection for Retaining Walls - Approved November 2007.

Ø      Right of Way - Establishing limits of dedication. Discussions are continuing with owners of affected parcels within Phase 1 work.

Ø      Construction Cooperative Agreement - Caltrans comments received on 2nd fact sheet submittal; City is preparing additional information requested.

Ø      Maintenance Agreement - City preparing exhibit for the first draft.

Ø      Declaration of Units – Caltrans Approved Metric Exception for this phase.

Ø      Utilities - Updated pothole plans have been reviewed by Caltrans. Encroachment permits are being sought.

Ø      Conceptual Landscape/Aesthetics - Concept was selected, with Murrieta, Caltrans, and IBC concurrence. Selection was incorporated into Draft Structures PS&E submittal.

16.    Old Town Gymnasium

This project will construct a gymnasium in old town, adjacent to the Boys and Girls Club. The Boys and Girls Club site is too small for the proposed Gymnasium. This project is on-hold until we can acquire the property required for construction. A meeting is scheduled for 8/19/08 to discuss measures that can move this project forward.

17.     Re-Stripe Route 79 South to 8 lanes from I-15 to Pechanga Parkway

This project will provide four lanes in each direction on Temecula Parkway (formerly State Route 79 South) from I-15 to Pechanga Parkway Design plans are complete.  City Council authorized going out to bid on 8/12/08. Construction will be coordinated with the Pechanga Parkway Dual Right Turn Lanes from Temecula Parkway, Project No. PW06-11.

18.     Pavement Management System Update 2008-2013

This project will update the City's Pavement Management System for the years 2008-2013. This project will update the City's Pavement Management System for the years 2008-2013. The Council approved an agreement with Wildan on March 18th. The Notice to Proceed was issued to the consultant in May. The City forwarded all requested information to Willdan to initiate the project. The consultant has started the field rating process. City will provide information about the new streets which were not included in the last PMS to the consultant.

19.    Localized Storm Drain Improvements

This project will fix the drainage problem at the south end of Front Street (at the MWD easement). Baseline right of way, utilities, and mapping are established.  This project is currently on hold.

20.   Long Canyon Detention Basin - Access Road

This project will construct an access road to the Long Canyon Detention Basin. Plans and specifications are 90% complete.  City is seeking FEMA funds to remove excess silt deposited within the basin before constructing the access road. Project is on hold until FEMA determination is finalized.

  

PROJECTS IN THE PLANNING STAGE


1.  I-15/ SR 79 South Interchange - Project Report (PR)

This project will modify the I-15/ SR 79 South Interchange to accommodate projected future traffic. This is the next step of project development after the completion of the Project Study Report. 

City continued development of design geometrics and environmental technical studies.  Status is as follows:

Ø      Draft Project Report - Approved January 2008.

Ø      Project Report - Under Caltrans review.

Ø      Advisory Design Exceptions - Approved 10/18/06.

Ø      Mandatory Design Exceptions - Approved 10/20/06.

Ø      Stormwater Data Report - Under Caltrans review.

Ø      Traffic Study - Approved 09/11/06.

Ø      Modified Access Report – FHWA Determination of Acceptability was approved in July 2007. Final approval pending approval of the Final Environmental Document.

Ø      Geometric Approval Drawings - Under Caltrans review.

Ø      Initial Study Assessment – Approved September 2005.

Ø      Acoustic Evaluation – Approved December 2005. 

Ø      Air Quality Assessment - Approved PM10 Nov 2005 and PM2.5 Jul 2006.

Ø      Nat Environmental Study – Approved May 2006.

Ø      Cultural Studies - Approved November 2006.

Ø      Draft Environmental Document - Approved Dec 2007 and publicly circulated 2/20/08 - 3/21/08.

Ø      Final Environmental Document - Under Caltrans review.

Ø      FHWA Air Conformity - Approved June 2008.

Ø      Erosion Control Plan - Under Caltrans review.

Ø      Life Cycle Cost Analysis - Under Caltrans review.  

 2.  French Valley Parkway Overcrossing and Interchange, Project Report (PR), Plans Specifications, and Estimate (PS&E) Preparation

This project will construct an interchange between Winchester Road Interchange and the I-15/I-215 split. The project is moving through the Caltrans process. Current status is as follows:

Ø      Draft Project Report - Approved June 2006.

Ø      Project Report - Final preparation pending approval of Environmental Document.

Ø      Draft Environmental Document - Under Caltrans review.

Ø      New Connection Report - Letter of Acceptability received in July 2008.

Ø      Traffic Operations Analysis - Approved 02/05/08.

Ø      Exception to 20-yr Traffic Design - Approved 12/17/07.

Ø      Stormwater Data Report - Under Caltrans review.

Ø      Mandatory Design Exceptions - Approved 07/18/06.

Ø      Advisory Design Exceptions - Approved 07/18/06.

Ø      Exception to Ramp Metering Policy - Approved 07/05/06.

Ø      Geometric Approval Drawings - Approved 07/18/06.

Ø      Revised Geometric Approval Drawings - Approved 01/11/08.

Ø      Storm Drain Study - Approved 03/21/08.

Ø      Floodplain and Scour Analysis Report - Under Caltrans review.

Ø      Declaration of Units - Request for Metric Exception denied by Caltrans.

Ø      Freeway Agreements - Revised exhibits under Caltrans review.

Ø      Risk Management Plan - Updating as necessary.

Ø      Project Charter - 1st draft is under Caltrans review.

Ø      Maintenance Agmt - Preparing 1st submittal for Caltrans review.

Ø      Financial Plan - Preparing 2nd submittal for Caltrans review.

3.  Temecula Creek Crossing - Access to Temecula Parkway

The project consists of performing an alignment study to set a specific horizontal and vertical alignment for an extension of Avenida de Missions southerly to gain vehicular access to Loma Linda Rd., including a bridge crossing over Temecula Creek.  The City Council approved the Professional Engineering Services Agreement with Nolte Associates, Inc. for a Bridge Alignment Study at the 06/10/08 meeting.  The kick-off meeting was held 06/24/08.

4.  Santa Gertrudis Creek Pedestrian/Bicycle Trail Extension and Interconnect 

The project will provide a Class I bicycle trail that connects the existing Santa Gertrudis Creek Pedestrian/Bicycle Trail at Ynez Road to the Murrieta Creek Multi-Purpose Trail at Diaz Road.  A request for proposal was issued on 08/06/08.  The proposal deadline is 08/27/08.

5.  Nicolas Valley - Assessment District (Liefer Road)

This project will study assessment district feasibility and formation, including completing the street and minor storm drain improvements on the unimproved portions of certain streets within Nicolas Valley (Liefer Road) area. The project is in the gathering data stage.